期刊文献+

茜坑隧洞围岩稳定性地质因素分析

Analysis of Geological Factors of Xikeng Tunnel Wall Rock Stability
下载PDF
导出
摘要 东深供水工程茜坑隧洞全长322 m,围岩为全风化、Ⅳ、Ⅴ类花岗岩。全段均为不良地质条件隧洞。在茜坑隧洞围岩的稳定性分析中,通过地质力学调查、地质测试和各种监测手段,将地质学对现象的研究与测试技术有机地结合起来,提出围岩地质体发展演变过程中的内部信息,实现地质参数定量的和可视的描述,即工程地质监测。根据围岩地质体演变全过程分析,对围岩变形演变过程及其所代表的稳定性状态,进行定性和半定量的分析评价。 Xikeng Tunnel in the Dongshen Water Supply Project has a total length of 322m. The wall rocks are granite of the completely weathered type and Ⅳ, Ⅴ types. The geological property of all the section has been improper for the tunnel construction. In the analysis of the stability of the wall rock in the Xikeng Tunnel, the geological research and the testing technology has been used synchronously, including the geo - mechanical survey, geological testing and various monitoring approaches. The internal information in the evolution of the geological substance has been figured out which has facilitated the quantitative and visual description of the geological parameters. This is also called the engineering geological monitoring. Based on the analysis of the whole process of the evolution of the geological substance in the wall rocks, the process of the transformation of the wall rocks and the stability situation it represents can be analyzed and assessed qualitatively and semi -quantitatively.
出处 《人民珠江》 2011年第6期25-27,共3页 Pearl River
关键词 茜坑隧洞 围岩 稳定性 地质因素 监测分析 Xikeng Tunnel wall rock stability geological factors monitoring analysis
  • 相关文献

参考文献3

二级参考文献14

  • 1张志强.高地应力条件隧道发生大变形破坏机理的研究[M].成都:西南交通大学,1999..
  • 2晏玉书 何满潮.我国煤矿软岩巷道围岩控制技术现状及发展趋势.中国煤矿软岩巷道支护理论与实践[M].徐州:中国矿业大学出版社,1996.1-19.
  • 3范秋雁 何满潮.软岩流变地压控制原理.中国煤矿软岩巷道支护理论与实践[M].徐州:中国矿业大学出版社,1996.141-150.
  • 4范秋雁,中国煤矿软岩巷道支护理论与实践,1996年,141页
  • 5何满潮,中国煤矿软岩巷道支护理论与实践,1996年,20页
  • 6晏玉书,中国煤矿软岩巷道支护理论与实践,1996年,1页
  • 7张志强,学位论文,1999年
  • 8铁道部建设司标准科情所,铁道隧道技术规范,1995年
  • 9陈至达,有理力学,1988年
  • 10工程岩体分级标准,GB 5 0 2 18— 94,