摘要
工程项目建设中钢筋加工厂的建设是工程质量及进度控制的重要环节。为实现低成本、高质量的钢筋存料,京沪高速铁路济南西站ZH标段确定在钢筋加工厂内建造移动式钢筋存料棚。实践结果表明,此方法能保证钢筋的质量,操作简便,安全省力,节约成本,场地文明。本技术作为新技术在京沪高速铁路建设项目中全面推广。
Construction of steel processing plant is important for the project quality and progress control in engineering projects.In order to obtain low-cost,high-quality steel materials store shed,the company decided to construct movable steel storage sheds in steel processing plant in ZH tender station line region in Ji'nan railway station on Beijing-Shanghai high-speed railway.Practice showed that this method can guarantee the quality of steel and it is simple,safe,efficient,cost-effective and is a civilized site.This technology as a new technology has been widely spred in Beijing-Shanghai high-speed railway construction projects.
出处
《铁道标准设计》
北大核心
2011年第12期90-92,共3页
Railway Standard Design
关键词
移动式钢筋存料棚
设计
施工
Movable steel store shed
Design
Construction