重大水利水电工程施工实时控制关键技术及其工程应用 被引量:88

Key technologies of real-time construction control for major hydraulic and hydroelectric projects
下载PDF
导出
摘要 高心墙堆石坝和高混凝土坝的施工质量与施工进度控制是工程建设的重要技术问题。针对常规人工控制手段难以确保高心墙堆石坝施工质量,以及高强度连续施工下高混凝土坝施工进度难以实时控制等问题,提出了高心墙堆石坝填筑碾压质量实时监控技术、坝料上坝运输过程实时监控技术和施工质量动态信息PDA实时采集技术,实现了大坝填筑碾压全过程的全天候、精细化、在线实时监控;在建立高混凝土坝施工进度实时控制数学模型基础上,提出了施工进度实时预警与动态调整方法,为高混凝土坝施工进度的实时预测、适时预警、动态调整与优化提供了分析手段;提出了网络环境下数字大坝系统集成技术,研制开发了数字大坝系统,为大坝竣工验收、安全鉴定及运行管理提供了支撑平台。成果已应用于10余项重大工程,取得了显著的经济效益和社会效益。 The quality control and schedule control are the significant technical problems in high core rock- fill dam and high concrete dam construction. The conventional quality control methods exhibit difficulty to ensure construction quality of high core rock-fill dam and to control timely schedule of high concrete dam under high-inten- sity continuous construction. Real-time compaction quality monitoring technology of high core rock-fill dam, real- time entire-process monitoring technology of dam materials transportation and real-time acquisition technology for dynamic information of construction quality using personal digital assistant devices (PDAs) are proposed, which re- alize the precise automatic online entire-process monitoring of compaction and transportation. In addition, based on an established mathematical model of concrete dam schedule real-time control, the method of timely warning and dynamic adjustment of construction schedule is proposed to provide means for schedule prediction, appropriate warning, dynamic adjustment and optimization of high concrete dam construction schedule. Furthermore, system integration technique for digital dam on Internet is presented, and a digital dam system is developed, which provides a supporting platform for dam final acceptance, safety assessment and operation management. The abovementioned technologies have been applied to more than 10 major hydro-electric projects with achieving remarkable economic and social benefits.
出处 《中国工程科学》 2011年第12期20-27,2,共8页 Strategic Study of CAE
基金 国家自然科学基金创新研究群体科学基金(51021004) 国家自然科学基金项目(50879056) "十一五"国家支撑计划课题(2008BAB29B05)
关键词 高心墙堆石坝 高混凝土坝 施工质量 施工进度 实时监控 数字大坝 high core rock-fill dam high concrete dam construction quality construction schedule real-time monitoring digital dam
  • 相关文献

参考文献13

  • 1Carlos Zambrano, Vincent Dmevich, Philippe Bourdeau. Advanced compaction quality control [R]. U. S. : School of Civil Engineering, Purdue University, 2006. ( http://docs, lib. purdue. edu/jtrp/285 ).
  • 2Michael A, Mooney, Robert V, et al. Field monitoring of miler vibration during compaction of subgrade soil [ J ]. Journal of Geotechnical and Geoenvironmental Engineering-ASCE, 2007, 133 (3) : 257 -265.
  • 3Petersen D, Siekmeier J, Nelson C, et al. Intelligent soil compaction-technology, results and a roadmap toward widespread use [Jl. Journal of the Transportation Research Board, 2006, 81 -88.
  • 4黄声享,刘经南,吴晓铭.GPS实时监控系统及其在堆石坝施工中的初步应用[J].武汉大学学报(信息科学版),2005,30(9):813-816. 被引量:50
  • 5王卓甫,李红仙,杨建基.水利水电施工进度问题研究综述[J].水利水电科技进展,2001,21(3):14-17. 被引量:16
  • 6丁世来,胡志根,刘全.大坝混凝土浇筑块排序方法的评价研究[J].红水河,2004,23(2):97-100. 被引量:15
  • 7钟登华,任炳昱,吴康新.Construction Simulation and Real-Time Control for High Arch Dam[J].Transactions of Tianjin University,2008,14(4):248-253. 被引量:5
  • 8钟登华.高混凝土坝施工仿真与实时控制[M].北京:中国水利水电出版社,2008.
  • 9钟登华,刘东海,张社荣,等.心墙堆石坝施工质量实时监控方法:中国,ZL200910069245.9[P].2010-10-13.
  • 10钟登华,刘磊,刘东海.心墙堆石坝碾压过程信息自动采集装置:中国,ZL200910069167.2[P].2010-10-06.

二级参考文献82

共引文献175

同被引文献703

引证文献88

二级引证文献745

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部