文中主要介绍了水轮机的重要部件转轮在电站现场加工的相关技术准备和技术要求,以及如何实现转轮工地加工的过程。为今后大型水轮发电机的转轮在电站现场制造提供可借鉴的经验。
It is mainly introduced the necessary teehnieal preparation and specification for runner manufacture at the site, and how to practice the runner machinery at the site, furnishing experience for reference in the future for the runner production at the site for large size hydro power generating units.
出处
《机械工程师》
2011年第12期164-165,共2页
Mechanical Engineer
关键词
电站现场
转轮
机加工
site of power station
runner
machining