期刊文献+

大断面导流洞进出口开挖支护设计与施工 被引量:3

Support Design and Excavation for the Inlet and Outlet Section of Large Cross-section Diversion Tunnel
下载PDF
导出
摘要 随着水电开发建设的加速,在水电工程中出现的大断面导流洞越来越多。在这些大断面导流洞的施工过程中,特别是导流洞的进口渐变段和出口段,容易出现安全问题甚至塌方事故。对目前国内部分已完工或正在施工的大断面导流洞进出口的开挖支护设计与施工方案进行了总结,并以在不同地质条件下的典型案例加以说明,可供类似工程参考和借鉴。 With the rapid development of hydropower project, there are more and more large cross-section diversion tunnels in engineering practice. The construction of this diversion tunnel is prone to lead safety problems, and even the collapse accident, especially in the transition inlet section and outlet section. The experiences on the support design and construction program of inlet and outlet sections of large across-section diversion tunnels in some hydropower projects in operation or under construction in China are summarized herein, and explained by the engineering practices of typical projects under different geological conditions. These experiences can be as reference to similar projects.
作者 马志峰
出处 《水力发电》 北大核心 2011年第12期44-46,71,共4页 Water Power
关键词 导流洞 进出口 开挖支护 设计 施工 diversion tunnel inlet and outlet excavation and support design construction
  • 相关文献

同被引文献29

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部