基于有限元分析的MSS45移动模架造桥机预压试验研究 被引量:5

Pre-loading Tests and Study of MSS45 Bridge-building Machine Based on Finite Element Analysis
下载PDF
导出
摘要 为了确认MSS45造桥机在施工过程中的安全可靠性以及为合理设置预拱度提供依据,需要在施工前进行预压试验。根据对MSS45造桥机的有限元分析结果,确定了造桥机各部位应力特征点及主梁挠度测点位置。试验结果表明,各测点的理论值与实测值较接近,造桥机安全可靠。 In order to confirm the safety and reliability of MSS45 bridge-building machine during construction and to provide basis for setting up reasonable pre-cambers it is necessary to carry out pre-loading tests on the bridge builder before the commencement of a project.The characteristic tensile points of various parts of the bridge building machine and the location of points to measure the deflection of main girders were determined according to the results of finite element analysis of the MSS45 bridge-building machine.The test results show that the theoretical values at the measuring points are closer to the measured values and the bridge-building machine is safe and reliable.
出处 《中国港湾建设》 北大核心 2011年第6期34-36,共3页 China Harbour Engineering
关键词 有限元 造桥机 预压 移动模架 finite element bridge-building machine preload movable scaffolding system
  • 相关文献

参考文献1

  • 1JTJ041-2000.公路桥涵施工技术规范[S].[S].,..

共引文献1724

同被引文献23

引证文献5

二级引证文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部