中亚管道哈国段CS4压气站压缩机联合吊装就位设计与实施 被引量:1

Design and Fulfillment of Hoisting Compressor in Place at CS4 Station of Kazakstan Section of China-Kazakstan Natural Gas Pipeline
下载PDF
导出
摘要 哈萨克斯坦社会依托条件较差,无法完全依靠当地的社会资源完成压缩机吊装任务,采用中型的吊装设备联合作业可以实施大型设备的吊装。文章介绍了使用4台履带吊将压缩机放置于预先做好的轨道上,然后采用卷扬机将压缩机拖入位置,再用液压千斤顶顶起就位的方案。实践表明,该方案设计安全可靠,为中亚管道其余站场的压缩机吊装就位找到了一条切实可行的途径。 Hoisting a compressor at CS4 Station of China-Kazakstan Natural Gas Pipeline was difficult if relying on Kazakstan local condition because of lacking heavy crane.Therefore a combined hoisting plan using medium-sized equipment to carry out the task was made.The compressor was hoisted by four caterpillar cranes then placed onto the preset tracks,a windlass pulled it in place and hydraulic jacks lifted it in position.The fulfillment of the combined hoisting plan proved that method was safe and reliable and it would find a practical way for other compressor hoisting operations of China-Kazakstan Natural Gas Pipeline.
出处 《石油工程建设》 2011年第6期58-61,91,共4页 Petroleum Engineering Construction
关键词 压缩机 吊装 方案 履带吊 compressor hoisting plan caterpillar crane
  • 相关文献

同被引文献2

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部