柬埔寨甘再水电站PH1尾水系统,目前存在现场开挖地质条件复杂、雨季降雨时间长、施工工期短等因素制约,在设计尾水方案过程中充分考虑这些因素,利用施工围堰再改造,最终使尾水建筑物设计方案技术可行、经济合理、施工方便。
For the tailwater system of Kamchay PH1 power plant, there are constraints such as complicated geological conditions encountered during site excavation, long time rainfall at wet season and short construction period. Full considerations were given to the above factors in the design of tailwater system option. Through reconstruction of the construction cofferdam, the design option of tailwater structure was feasible in technology, reasonable in economy and ease for construction.