摘要
着重介绍了柬埔寨甘再水电站接入系统方式、电气主接线、主要电气设备选择等内容,同时对工程项目运作过程中遇到的问题进行了总结。
The paper highlights the access system mode, main electrical wiring and main electric equipment selection of Kamchay hydro- power station, and summarizes the problems encountered in the process of engineering project operation.
出处
《西北水电》
2011年第B12期53-55,62,共4页
Northwest Hydropower
关键词
柬埔寨甘再水电站
电力系统
电气主接线
电气设备
选择
Kamchay hydropower station
power system
main electrical wiring
electric equipment
selection