摘要 应用综合物探等手段对龙口水利枢纽工程坝基爆破开挖影响程度及破坏机理、基础验收标准、软弱夹层的空间分布等进行了检测研究。根据检测成果,对1#~10#坝段拦河坝及发电厂房建筑物基础固结灌浆进行了优化设计,优化后节约了工程投资,加快了工程建设进度。 The comprehensive geophysical prospecting were applied in Longkou Water Control Project to research the excavation by blasting effect and damage mechanism, basic acceptance criteria, soft interlayer space distribution of dam foundation. According to the test results , the river barrage located on the No. 1 - No. 10 dam sections and powerhouse consolidation grouting foundation were optimum designed, which greatly saved the project investment and speeded up the construction progress.
出处 《人民黄河》 CAS 北大核心 2011年第12期99-100,共2页 Yellow River
关键词 基础岩体 综合物探 固结灌浆 龙口水利枢纽 foundation rock comprehensive geophysical prospecting consolidation grouting Longkou Water Control Project
  • 相关文献

参考文献3

共引文献8

同被引文献36

引证文献3

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部