摘要
分析尿素装置、三聚氰胺装置联运后高压氨泵高负荷运行时运行周期短、设备本体检修频繁的原因,制定相应措施,保证高压氨泵长周期运行,降低设备备件损耗,实现装置高负荷经济运行。
The causes for short operation cycle and frequent equipment maintainance of HP ammonia pump at a high load when urea and malamine plants are in co-operation are analyzed and corresponding measures formulated to ensure a long-term operation and a reduced loss of equipment spare parts of HP ammonia pump for the realization of an economic operation at high load.
出处
《大氮肥》
CAS
2011年第6期425-427,共3页
Large Scale Nitrogenous Fertilizer Industry
关键词
尿素装置
高压氨泵
高负荷运行
urea plant
HP ammonia pump
technical transformation
operation at high load