摘要
针对目前水电工程隧洞施工TBM机械使用尚无相关定额对其进行技术经济指导的现状,结合TBM设备的施工特点及锦屏二级水电站引水隧洞工程TBM设备施工数据的采集和整理,分析了TBM设备施工费用的构成,并提出了TBM设备台时费定额编制的方法和思路,为TBM设备台时费定额的编制提供了参考依据。
There is no quota to guide the use of TBM related technical economy in tunnel construction of hydropower project. Combined the construction characteristics of TBM with data collection and collation for diversion tunnel of Jinping Hydropower Station Ⅱ , the composition of construction costs are analyzed. And then the methods and ideas of TBM quota establishment in hydropower project is put forward, which provides reference for TBM quota establishment.
出处
《水电能源科学》
北大核心
2012年第1期185-188,共4页
Water Resources and Power
关键词
水电工程
全断面岩石掘进机
台时费
定额编制
hydropower engineering
tunnel boring machine
mechanical royalties
quota establishment