上海轨道交通3号线改造工程换梁方案研究 被引量:2

On Beam Replacement Scheme of the Reconstruction of Shanghai Rail Transit Line 3
下载PDF
导出
摘要 在轨道交通3号线改造工程中,如何在最短的中断运营时间段内安全可靠地实施换梁,是改造工程成败的关键之一。从确保轨道交通运营、降低对城市交通和铁路运营的影响等方面考虑,提出了吊老梁移新梁、提梁机换梁、南侧制梁北侧落梁、北侧制梁南侧落梁等四种换梁施工方案。在对不同的换梁施工方案进行比选后,推荐提梁机换梁方案。介绍了该方案的主要工作内容,分析了施工过程中的难点和采取的措施。 In the reconstruction engineering of Shanghai Rail Transit Line 3, how to implement the beam replacement safely and reliably within the shortest interruption of train operation is one of the key factors to ensure the success of the project. By taking into account the measures to ensure rail transit operation and to reduce the impact of beam replacement on urban transport and railway operation, four different beam replacement construction schemes are proposed: lifting the old beam for the moving in of the new one; using a hoist to replacing the beam; making beam on the south side and landing beam on the north side; making beam on the north side and landing beam on the south side. With a comparison between different beam replacement schemes, beam hoist is recommended, the main contents of this scheme are introduced, difficulties in the engineering and necessary measures are analyzed.
作者 蔡蔚
出处 《城市轨道交通研究》 北大核心 2012年第1期97-100,共4页 Urban Mass Transit
关键词 城市轨道交通 高架桥 改造工程 换梁方案 urban rail transit viaduct reconstruction pro-ject beam replacement scheme
  • 相关文献

参考文献5

二级参考文献1

  • 1成大先.机械设计手册[M](第四版)[M].北京:化学工业出版社,2002..

共引文献16

同被引文献12

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部