110kV变电站量大面广,消防安全不可小视。以典型的110kV变电站为例,从消防车道设置、主变压器侧生产建筑物外墙的封堵、主变压器挡油池有效容积、消防棚的位置及防火门的要求等方面进行分析,针对容易忽视的问题提出了相应的要求或解决措施。以满足工艺功能要求和国家消防安全标准,为满足变电站顺利建设和长治久安提供了参考。
Fire control safety cannot be ignored for 110kV transformer substations in consideration of their large quantities and vast distribution. A typical 110kV substation is examplified in this paper. From the aspects such as setting up the fire lane, blocking outer side wall of main transformer, setting effective volume of emergency oil pond of main transformer, locating fire control shed and fire door and so on to take analysis. Upon problems of easy to be neglected, proposes corresponding restrictions or solution measures, so as to meet process and function requests as well as national standards for safety and fire control, which provides reference for constructing a transformer substation with long time safety.
出处
《华中电力》
2011年第6期4-6,10,共4页
Central China Electric Power
关键词
110KV变电站
消防车道
主变侧外墙封堵
主变挡油池
消防棚
防火门
110kV substations
fire control lane
main transformer outer side wall blocking
emergency oil pond of main transformer
fire control shed
fire door