丹江口水电厂110、220kV开关站接地网的改造 被引量:1

Improvement for 110 and 220 kV Switch Station Grounding Network in Danjiangkou Hydropower Plant
下载PDF
导出
摘要 经过对丹江口水电厂110、220 kV开关站接地网存在的问题进行分析,并结合前期的全面勘测和局部开挖检查,根据丹江口电厂开关站接地网实际状况,综合考虑南水北调中线丹江口大坝加高施工的影响因素,有针对性地制定了改造方案,有效地解决了目前开关站地网热稳定、电压分布、腐蚀等亟待解决的问题。 The existing problems of 110 and 220kV switch station grounding network in Danjiangkou hydropower plant are analyzed. By taking into account the previously comprehensive survey and local excavation inspection, the grounding network actual status in switch station and the influential factors in South-North Water Diversion Project, the improvement approaches for above-mentioned existing problems are formulated, which effectively solve the problems in switch station such as network hot stability, and voltage distribution , and corrosion.
作者 肖丽春 黄健
出处 《水电与新能源》 2012年第1期57-59,共3页 Hydropower and New Energy
关键词 开关站 接地网 接地极 热稳定 腐蚀 降阻 switch station grounding grid electrode hot stability corrosion resistance reduction
  • 相关文献

参考文献2

  • 1DL475-1992.接地装置工频特性参数的测量导则[S].[S].,..
  • 2解广润.电力系统接地技术[M].北京:中国电力出版社,1996.

共引文献20

同被引文献5

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部