摘要
介绍了风电产品铸件的技术要求,指出:设计合理的浇注系统可以有效地解决夹渣问题,还有利于铸件补缩;小冒口生产成本低于一般的冒口工艺,工艺出品率大大提高,而工艺稳定性则高于无冒口铸造工艺;利用冷铁改变铸件冷却速度则有利于解决石墨漂浮和碎块状石墨缺陷,但要慎用冷铁,尤其是高牌号球铁铸件。
The quality requirement for the wind power castings was introduced.It was pointed out that rational gating system made it possible not only to effectively prevent the dross defect and also improve the casting feeding.The casting method with small risers could reduce the productive cost and increase the process yield rate,compared with the method using big riser,and,in addition,it could increase the casting quality stability compared with using the riser-less method.The usage of chills should be careful,especially for the high grade nodular iron castings,however,using chills to change the casting cooling rate would be helpful to prevent graphite floatation and chunk graphite formation.
出处
《现代铸铁》
CAS
2011年第6期43-47,共5页
Modern Cast Iron
关键词
厚大球铁件
浇注系统
冒口
冷铁印迹
石墨漂浮
heavy section nodular iron casting
gating system
riser
chill print
graphite floatation