摘要
侧槽式溢洪道除险加固工程设计不同于新建工程设计,是新建工程设计的一个逆过程。通过对已有建筑物尺寸的复核,结合现场实际地形情况,在尽可能不改变原有建筑物结构型式的前提下,确定合适的加固方案,以解决现有工程存在的问题。该文以抄道沟水库溢洪道加固设计为例,简要介绍侧槽式溢洪道加固设计。
Different from the new project design,the design of side channel spillway used on danger control and reinforcement project is a inverse process of a new designed project.Based on the size review of the existing building,combined with the actual terrain scene,giving the proper reinforcement scheme to slove problems in the existing project under the permise of unchanging the structure of the former builing as much as possible.Take the reinforcement project of spillway of Chaodaogou seservoir as an example,the article introduces the design of the reinforcement project of side channel spillway briefly.
出处
《水科学与工程技术》
2011年第6期43-45,共3页
Water Sciences and Engineering Technology
关键词
侧槽末端水深
临界水深
临界底坡
水面线
water depth in end side channel spillway
critical water depth
critical bed slope
water surface line