摘要 以往榆林沙漠地区基坑降水采用先开挖后降水,容易出现基坑边坡塌方,降水难度大,费工费时,降水效果差,本工程基坑降水采用了多管降水法,从管井的沉设方法,PPR新材料的运用,井管的制作等方面,开发研究出小范围内基坑降水的新方法,降水效果好,可在具有相同水文地质条件的工程降水中应用。 For Yulin desert area,the precipitation of the foundation pit is excavation firstly,which causes prone to landslide of the pit slope.The precipitation method is difficult,labor-and time-consuming,poor rainfall.The engineering foundation pit with a multi-tube precipitation method,from the sink tube wells design method,PPR use of new materials,its manufacture etc.,developed a new method for a small range of foundation pit,the precipitation effect is good and can be use to rainfall for the other projects which have the same hydrological and geological conditions.
作者 王亚军
出处 《地下水》 2011年第5期14-15,共2页 Ground water
关键词 基坑降水 设计 PPR材料井管 Precipitation of the foundation pit to design and PPR well tube
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部