摘要 1000 kV串联补偿装置平台的面积、质量、安装高度都远大于500 kV串联补偿装置平台,有必要详细研究1 000 kV串联补偿装置平台吊装技术。根据工程现场不同的平面布置方式,分析了3种平台地面组装布置方式;同时,提出了单台吊车起吊、2台吊车联合起吊、4台吊车联合起吊3种平台吊装方案,并进行了技术经济指标对比。其中,4台吊车联合起吊的方案已在特高压直流试验基地进行了现场试验,验证了方案的有效性。 The platform of 1 000 kV series compensation device is much larger than that of 500 kV on area,quality and installation height.Therefore it is of great importance to investigate the hoisting technology for platform of 1 000 kV series compensation device in detail.Concerning different plane layouts in field,three schemes for platform assembly on ground are proposed.In addition,three platform hoisting schemes are proposed by one crane,two or four cranes combined respectively,and compared from technical and economic view.The scheme by four cranes combined is applied in UHV DC test base,of which the effectiveness is verified.
出处 《电力建设》 2012年第1期96-100,共5页 Electric Power Construction
基金 国家电网公司科技项目(特高压交流试验示范工程扩建工程科技项目)
关键词 1000kV串联补偿装置 1000kV串补装置平台 1000kV串补平台基础 平台地面组装布置方式 平台吊装方案 联合起吊 1000 kV series compensation equipment platform of 1000 kV series compensation equipment platform foundation of 1000 kV series compensation equipment platform assembly on ground hoisting technology of platform combined hoisting
  • 相关文献

参考文献7

二级参考文献17

共引文献138

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部