摘要
介绍了三峡左岸电站ALSTOM机组定子的主要技术参数,提出了定子整体耐压及纯水系统试验的项目及试验标准,拟订了试验顺序及不同试验的具体实施方案,指出了安全注意事项。
The main technical parameters of stator of the ALSTOM-made unit installed in the Three Gorges Left Bank Hydropower Station were introduced.The test items and test standards of the stator whole withstanding voltage test and the cooling water system test were put forward;the test sequence and the concrete implementation plans of different tests were drawn up;and some security matters were pointed out.
出处
《华电技术》
CAS
2012年第2期34-35,42,共3页
HUADIAN TECHNOLOGY
关键词
定子绕组
电气试验
纯水系统
试验方案
安全事项
stator winding
electrical test
cooling water system
testing program
security matters