摘要 隧道施工中为安全穿越软弱破碎围岩地段,在采取有效的预加固措施确保施工安全的前提下,要综合考虑结构安全与质量、进度与工期、工程经济等多方面因素。结合贵广铁路大田一号隧道工程实例,指出微台阶大拱脚七步开挖法较分部开挖法可以更好地控制围岩变形,并且具有工期短、安全性高等优势,对同类工程具有借鉴意义。 For safely pass through the weak rock in tunnel construction, in the premise of taking effective prereinforcement measures to ensure construction security, the structure security and quality, progress and duration, and engineering economy should be integrated considered. Combined with Datian No.1 Tunnel project of Guiguang Railway better control weah struction period and it was pointed out that micro-stepped large arch feet seven steps excavation method can rock deformation than division excavation method, and has the advantages of short con- high security, which can be reference to similar projects.
出处 《筑路机械与施工机械化》 北大核心 2011年第12期81-83,共3页 Road Machinery & Construction Mechanization
关键词 隧道 软弱围岩 大断面 施工方法 tunnel weak rock large cross section construction method
  • 相关文献

参考文献2

二级参考文献10

共引文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部