沈本产业大道歪头山至石桥子段路基施工分析

Cobstructional Evaluation of Roadbed for the Section between Waitoushan and Shiqiaozi of the Industrial Roa drom Shenyang to Benxi
下载PDF
导出
摘要 通过对沈本产业大道歪头山至石桥子段路基施工进行分析,包括对路基施工准备工作、试验路段铺筑、路基填筑施工、特殊路基处理、结构物台后回填施工、路基整修、路基施工质量控制及检测,施工质量控制及检测结果数据表明填筑路基的含水量大小直接影响压实效果,检测数据统计分析表明道路基层施工各项指标达到规范标准,沈本产业大道歪头山至石桥子段路基施工是一个优质工程。 By analysing the roadbed construction for the section between Waitoushan and Shiqiaozi of the industrial road from Shenyang to benxi,including preparation,trial section operation,filling the roadbed up,special roadbed treatment,backfill operation after removing a structure,roadbed construction quality control and test.It shows by test data that the moisture content of roadbed directly effect the compression result,all indexes fulfill the standard,and the section betweenWaitoushan and Shiqiaozi of tha industrial road from Shenyang to Benxi is a high grade road.
作者 王刚
出处 《辽宁科技学院学报》 2011年第4期29-31,共3页 Journal of Liaoning Institute of Science and Technology
关键词 路基施工 试验路段 质量控制 Roadbed construction Trial road section Quality control
  • 相关文献

参考文献4

  • 1JTGB01-2003.公路工程技术标准[S].[S].,..
  • 2公路路基设计规范[S].SFGD30-2004.
  • 3JTG F10-2006,公路路基施工技术规范[S].
  • 4最新公路工程施工要点与通病防止大全[M].北京:兵器工业出版社,2001.

共引文献1288

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部