100 t级上仰预应力锚索在积石峡水电站隧洞工程中的应用 被引量:1

Application of Upward Prestressed Anchor Cable with Capacity of 100 t in Tunneling,Jishixia Hydropower Station
下载PDF
导出
摘要 上仰预应力锚索较下倾锚索在施工中存在内锚固段灌浆、锚墩头制安等突出问题和困难,在积石峡水电站导流洞与中孔泄洪洞交叉段100 t级上仰预应力锚索施工中,采用高强度低松弛钢绞线自由式预应力锚索、三管两次灌浆、钢结构墩头等工艺和结构,成功解决了上仰预应力锚索施工中存在的问题,取得了良好的效果,可供其他类似工程借鉴使用。 Compared with the downward anchor cable,the upward prestressed anchor cable is with outstanding issues and difficulty in grouting at the internal anchoring section,manufacturing and installation of anchor head in construction.In the construction of the upward prestressed anchor cables with capacity of 100t at intersection of diversion tunnel and flood discharge tunnel of middle outlet of Jishixia Hydropower Station,techniques and structures such as freestyle prestressed anchor cables made of high-strength low-slack strand,twice grouting with three pipes and anchor head of steel structure,etc are applied,successfully solving issues in the construction of the upward prestressed anchor cables and obtaining the expected results.Those can be utilized by other similar projects for reference.
出处 《西北水电》 2012年第1期29-33,共5页 Northwest Hydropower
关键词 预应力锚索 上仰孔 三管两次灌浆 钢结构墩头 积石峡水电站 Prestressed anchor cable upward hole twice grouting with three pipes anchor head of steel structure Jishixia Hydropower Station
  • 相关文献

参考文献4

二级参考文献5

共引文献5

同被引文献8

  • 1GB/T14370-2007预应力筋用锚具、夹具和连接器[S].北京:中国建筑工业出版社,2007.
  • 2GB/T5224-2003预应力混凝土用钢绞线[S].北京:中国标准出版社,2003.
  • 3中国水力发电工程编审委员会.中国水力发电工程(施工卷)[M].北京:中国电力出版社,2000.485-494.
  • 4DL/T 5148-2012,水工建筑物水泥灌浆施工技术规范[S].北京:中国电力出版社,2012.
  • 5GB175-2007普通硅酸盐水泥[s].2007年版.北京:中国标准出版社,2007.
  • 6DIMT5083-2004,水电水利工程预应力锚索施工规范[S].北京:中国电力出版社,2004.
  • 7DIMT5144-2001,水工混凝土施工规范[S].北京:中国电力出版社,2001.
  • 8吉杰宇.那邦水电站大坝右岸高边坡加固中的预应力锚索设计[J].西北水电,2012(4):46-49. 被引量:3

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部