摘要
通过分析锦屏1、2级电站首尾相接的特点,初步探讨了枯水期两级电站经济运行的有功优化可行方式,为电站投产后的实际安全经济运行提供了参考。
The feasible mode for active power optimization of the economic operation between the two-stage hydropower stations in low water period are discussed through the analysis on the features of Jinping Power Plant in which the first stage station and the second stage station are connected end to end.It provides a useful reference for the safe and economic operation after the hydropower stations being put into service.
出处
《四川电力技术》
2012年第1期54-56,共3页
Sichuan Electric Power Technology
关键词
枯水期
经济运行
有功优化
low water period
economic operation
active power optimization