摘要
根据新集一矿已有的工程地质资料和科研成果建立模型,采用FLAC3D进行了数值模拟,并结合现场观测,研究了小错距上下煤层工作面反向同采时,上工作面巷道围岩应力、塑性区和变形情况,研究结果表明,上工作面巷道围岩变形在两工作面推进过程中呈现两个阶段的变化,该巷道围岩一定范围内发生塑性破坏是其围岩变形不断增长的主要原因,因此上工作面巷道支护的关键是加固其围岩的塑性破坏区,提高围岩的自承载能力。
The numerical model was established by FLAC3D software according to the exist- ing engineering geological data and scientific research results on No. 1 Colliery of Xinji Energy Company. Combined with the observation data from the coal mine, the stress of surrounding rock, the plastic region and the deformation of the roadway in the upper mining face were studied during the coal mining in opposite directions in the upper and lower coal seams with small hori- zontal separation. The results showed that the surrounding rock deformation of the roadway in the upper mining face waried in two stages in the advancing process of two mining faces. The plastic damage in some :regions caused the continuous deformation of the surrounding rock. So the key of roadway support in the upper mining face is to strengthen the plastic damage area of surrounding rocks so as to improve the own bearing capacity of surrounding rocks.
出处
《中国煤炭》
北大核心
2012年第2期73-75,共3页
China Coal
关键词
回采工作面
反向同采
数值模拟
小错距
回采巷道
围岩变形
mining :face, mining in opposite directions, numerical simulation, small horizontal separation, mining roadway, deformation of surrounding rocks