摘要 针对锦赤铁路洗矿厂特大桥地质条件,对比分析了竖井、沉井、钢板桩围堰三种阻水方案,确定采用钢板桩围堰方案,详细介绍了相关设计计算方法,并对施工工艺作了具体阐述,并总结了钢板桩围堰的特点及施工注意事项,以指导今后同类工程。 In light of geological condition of especially big bridge on Jin-Chi railway,the paper analyzes and compares three kinds of water resisting schemes including vertical shaft,caisson,and steel plate pile cofferdam,determines to apply steel plate pile cofferdam,specifically introduces calculation methods of corresponding design,and describes construction technology.In the end,it summarizes the features and matters needing attention in the construction of steel plate pile cofferdam,with a view to guide similar engineering in future.
作者 张芳
出处 《山西建筑》 2012年第8期78-80,共3页 Shanxi Architecture
关键词 承台 钢板桩围堰 设计 施工 bearing platform steel plate pile cofferdam design construction
  • 相关文献

参考文献4

  • 1公路施工手册《桥涵》[M].北京:人民交通出版社,2000.
  • 2TB10203-2002,铁路桥涵施工技术规范[S].
  • 3TB10002.1-99.铁路桥涵设计基本规范[S].[S].,..
  • 4刘自明.桥梁深水基础[M].北京:人民交通出版社,2004.

共引文献61

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部