摘要
根据吉沙水电站枢纽布置,进行各部位金属结构的布置及设计。介绍了各闸门和启闭机等设备的参数及结构特点。目前该电站金属结构设备均已完成制作、安装及设备调试,并通过竣工验收。各扇闸门止水效果良好,闸门启闭运行平稳,金属结构设备运行正常。
The layouts and designs of metal structures iu Jisha Hydropower Station Project are determined according to the layout of hydraulic structure. The parameters and structure of gates and headstock gears are introduced. The production, installation and commissioning of all the metal structures have been completed, and have passed the final acceptance. The actual operation of station shows that the gates have good sealing and can be opened and dosed smoothly.
出处
《水力发电》
北大核心
2012年第3期76-77,89,共3页
Water Power
关键词
金属结构
布置
设计
吉沙水电站
metal structure
layout
design
Jisha Hydropower Station