全泥氰化提金厂工艺技术改造实践 被引量:3

Practices of Technological Reform in the Gold Cyanidation Plant
下载PDF
导出
摘要 从降低生产成本、提高金的回收率出发,山东黄金归来庄矿业有限公司进行了全泥氰化提金厂的技术改造,将原有的全泥氰化浸出-锌粉置换与炭浆吸附联合提金工艺改为全泥氰化浸出-炭浆吸附工艺,同时对部分设备进行了更新改造,改造后不仅单系统处理能力从350 t/d提高到500 t/d,而且金的回收率也有一定提高,运行成本明显下降,取得了显著的经济效益。 Technological reforms were conducted in the gold cyanidation plant of Guilaizhuang Mining Industry Co Ltd to reduce operation cost and improve the recovery rate of gold. The original combined gold extraction process of all-slime cyanidation leaching-zinc powder replacement and carbon-in pulp(CIP) adsorption was changed into all-slime cyanida- tion leaching-CIP adsorption process, meanwhile transformation and renovation were conducted for some equipment. The production capacity of single system improved from 350 t/d to 500 t/d and the recovery rate of gold increased, which has brought a dramatical decrease in the operation cost and significant economic benefits.
出处 《矿冶工程》 CAS CSCD 北大核心 2012年第1期81-83,共3页 Mining and Metallurgical Engineering
关键词 全泥氰化 炭浆吸附 工艺优化 设备改造 all slime cyanidation carbon-in-pulp adsorption process optimization equipment reform
  • 相关文献

参考文献2

二级参考文献1

  • 1张凤阁.贫液返回工艺的理论解析—经济合理的提金工艺[J]黄金,1985(03).

共引文献2

同被引文献33

引证文献3

二级引证文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部