摘要
阿海水电站在建设过程中,业主根据施工进展情况,决定将首台机组发电日提前3个月,由此产生施工合同变更。施工方制定了相应的措施,并运用实物法计算了赶工费用,监理机构在赶工费用审核过程中,认真分析了施工变化情况及产生的相应费用,促使业主和承包商就赶工费用达成一致意见,保证了阿海水电站机电安装赶工的顺利进行,为实现阿海水电站提前发电创造了良好的合同环境条件。
In the construction of Ahai Hydropower Station, the generation was advanced for 3 months ahead of the schedule, so the original construction contract should be changed. The construction contractor put forward corresponding measures and calcu- lated the extra cost by object method. In the cost examination, the supervision department seriously analyzed the construction change condition and the corresponding cost, and made the owner and the contractor reach an agreement, so as to guarantee the smooth installation of mechanical electrical equipment.
出处
《人民长江》
北大核心
2012年第4期17-18,21,共3页
Yangtze River
关键词
机电安装工程
赶工费用
实物法计算
阿海水电站
mechanical and electrical equipment installation project
cost of constructive acceleration
calculation by object method
Ahai Hydropower Station