期刊文献+

北京翠湖人工湿地污水净化的效果分析 被引量:9

Analysis on the Sewage Purification Effects of Cuihu Constructed Wetland, Beijing
下载PDF
导出
摘要 通过在北京翠湖构建人工湿地来处理污染水体,研究该人工湿地对pH、浊度、CODcr、TN、TP的去除作用。从人工湿地对污染物的去除效果来看,浊度、CODcr、TN和TP运行3月的平均去除率分别为42.659%、7.161%、25.583%和24.662%。结果表明:翠湖人工湿地处理的水体中pH随时间变化而有所降低,出水口pH值逐渐得到改善。翠湖人工湿地5个不同时间段(2009-06-03、2009-06-26、2009-07-09、2009-07-29、2009-08-17)浊度的平均去除率分别为66.459%、62.562%、33.343%、6.616%、44.314%。翠湖人工湿地对CODcr的去除率随时间变化有较小波动,5个时间段平均去除率分别为4.347%、4.716%、10.748%、9.370%、6.622%。TN平均去除率分别为15.465%、27.669%、30.507%、33.177%、21.098%,TP平均去除率分别2.688%、49.790%、21.538%、13.580%、35.714%。 The wastewater treatment effect of pH, Turbidity, CODor, TN, TP had been studied by the constructed wetland in Cuihu wetland, Beijing. From the operation effect, the average removal rate of turbidity, CODor, TN and TP was 42.659%, 7.161%, 25.583%, 24.662% respectively after 3 months. The results showed that pH decreased with time, the outlet value of pH was gradually improved. The average Turbidity removal rate was 66.459%, 62.562%, 33.343%, 6.616%, 44.314%, respectively in 5 different periods (2009-6-3, 2009-6-26, 2009-7-9, 2009-7-29, 2009-8-17). The removal of CODor had less fluctuation over time, removal rate was 4.347%, 4.716%, 10.748%, 9.370%, 6.622% respectively in Cuihu constructed wetland. The average TN removal rate was 15.465%, 27.669%, 30.507%, 33.177%, 21.098% respectively. The average TP removal rate was 2.688, 49.790%, 21.538%, 13.580%, 35.714% respectively.
出处 《中国农学通报》 CSCD 2012年第5期278-282,共5页 Chinese Agricultural Science Bulletin
基金 北京市科技计划重大项目"北京市湿地生态系统保护与恢复关键技术研究和示范"(D08040600580000) 林业公益性行业科研专项"太湖流域湿地生态系统功能作用机理及调控与恢复技术研究"(200904001)
关键词 人工湿地 污水净化 效果 constructed wetland sewage purification effect
  • 相关文献

参考文献12

二级参考文献152

共引文献442

同被引文献150

引证文献9

二级引证文献57

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部