摘要
老口枢纽坝址位于左、右江汇合口下游4.7 km的郁江河段,枢纽建成后阻隔了鱼类洄游通道,并对鱼类产卵场造成不利的影响,修建垂直竖缝式鱼道作为主要过鱼设施,修建鱼类增殖保护站开展人工增殖放流,作为主要鱼类保护措施,论述了这些保护设施的总体布置、设计和生产方式。
Laokou Complex is located on Yujiang fiver section, about 4.7km downstream of the conjunction of Zuoji- ang River and Youjiang River. In order to avoid its construction will block the fish migration way and affect spawning, vertical slot fish-way is designed as major fish pass structure, and fish reproduction protection station will be built for artificial breeding and releasing. An introduction was made on the general layout, design and production mode of these fish protection facilities.
出处
《广西水利水电》
2012年第1期16-20,28,共6页
Guangxi Water Resources & Hydropower Engineering
关键词
老口枢纽
过鱼设施
鱼道工程
鱼类增殖保护站工程
Laokou Complex
fish pass structure
fish-way construction
fish reproduction protection station