摘要
卡基娃水电站8号公路滑坡规模大,地质条件复杂,对导流洞进口造成极大威胁,设计采用锚索、锚杆、框格梁等综合处理措施,取得了良好的效果。本文系统介绍了计算分析方法、治理方案优选、施工工艺等关键技术,对类似工程具有一定的参考价值。
No. 8 road of Kajiwa hydropower project has a large - scale slope landslide and complex geological con- ditions which have a serious threat to the intake of diversion tunnel. The treatment measures of anchor cable and bolt, anchor cable grid beam are used in the design and obtain" good effects. The paper introduces the calculation a- nalysis, design scheme selection and key technology of construction technique, which offer a certain reference for the similar projects.
关键词
滑坡
锚索
框格梁
预应力
固结灌浆
slope landslide
anchor cable
anchor pile grid beam
prestress
consolidation grouting