摘要
分析了远动系统传统串口方式和网络方式的区别,介绍了远动系统改造的原则,阐述了远动系统改造的三种方案,以220kV金阳变为例,详细说明了远动系统改造的实施过程。
This paper analysed the difference between the serial interface mode and the network mode, introduced the principles of telecontrol system reformation, and discussed the three schemes of teleeontrol system reformation. Taking the 220kV Jinyang substation as an example, this paper detailed the implementation process of teleeontrol system reformation of telecontrol system transformation.
出处
《贵州电力技术》
2012年第1期77-79,共3页
Guizhou Electric Power Technology
关键词
远动系统
调度数据网
改造
主网变电站
telecontrol system
dispatching data network
reformation