摘要
为解决海岸滩涂与近海滩涂风电施工问题,提出一种新型滩涂风电安装施工工艺,该工艺降低了施工费用,缩短了施工周期,绿色环保,可为滩涂施工提供指导与借鉴。
To solve wind-power construction problems for coastal mudflat and offshore mudflat,a new type of construction technology for mudflat wind-power equipment installation is put forward.This technology reduces the construction cost and shortens the construction period.With green environmental protection,it provides direction and references for mudflat construction.
出处
《起重运输机械》
2012年第3期32-35,共4页
Hoisting and Conveying Machinery
关键词
滩涂
施工工艺
风电
mudflat
construction technology
wind-power