金川Ⅲ矿区破碎站硐室施工变形监测与优化控制 被引量:6

Deformation Monitoring and Optimal Control During Chamber Construction in Broken Station of Jinchuan No.3 Mine
原文传递
导出
摘要 为了有效控制金川Ⅲ矿区1 165 m水平破碎站大断面硐室围岩变形,根据对破碎系统工程的大件道工程围岩变形监测、变形影响因素的分析得出该矿区岩体具有临界蠕变应力低和碎裂剪胀蠕变特征,且变形持续时间长。针对该岩体的变形特点,在破碎站大断面硐室施工中采用"留空让压强支"原则,并提出留空让压强支方案的综合评价指标。设计了3因素4水平的正交数值模拟试验方案,通过综合评价指标的分析确定了合理让压位移量,即毛硐让压变形90 mm,初衬让压变形0,一次支护让压变形50 mm。为了破碎站硐室的安全评价和长期稳定性预测,采用FBG点式光纤光栅传感器监测围岩变形。 To effectively control the deformation of rocks in the large section chamber of broken station in Jinchuan No.3 Mine,we monitored the deformation of surrounding rocks and analyzed the factors affecting such deformation,indicating that the rock mass is characterized by a low critical creep stress,a broken shear dilatation creep,and a long duration of deformation.Aiming at these deformation characteristics,we adopt the principle of "yield through leaving space and strengthening support" and put forward a comprehensive evaluation index.We also proposed an orthogonal numerical simulation test program among the three factors,designed four levels through the comprehensive evaluation index analysis,and determined a reasonable amount of yield displacement in which the gross distortion of the chamber is 90 mm,the initial lining to yield deformation is 0,and the twain support to yield deformation is 50 mm.For the safety assessment and the long term stability prediction of broken surrounding rocks,we use FBG sensors to monitor the rock deformation.
出处 《采矿与安全工程学报》 EI 北大核心 2012年第1期60-66,共7页 Journal of Mining & Safety Engineering
基金 国家重点基础研究发展计划(973)项目(2010CB731501) 国家自然科学基金项目(51074003) 国家"十一五"科技支撑计划项目(2008BAB32B01) 安徽高校省级自然科学研究重点项目(KJ2011A080)
关键词 金川矿区 大型地下硐室 让压位移量 数值试验 变形监测1 Jinchuan mine large section underground cavern yield displacement numerical experiment deformation monitoring
  • 相关文献

参考文献9

二级参考文献27

共引文献227

同被引文献71

引证文献6

二级引证文献47

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部