泸定水电站清水混凝土质量控制 被引量:1

Quality Control of Exposed Concrete in Construction of the Luding Hydropower Project
下载PDF
导出
摘要 在四川省泸定水电站厂房安装间框排架清水混凝土施工前,针对清水混凝土的原材料、配合比、模板、分缝、棱角、混凝土浇筑、振捣、养护等环节进行了全面的工艺试验,找出最佳组合用于正式施工,并在施工质量控制过程中通过精细化管理,保证了清水混凝土的工程质量,取得较好的外观效果。 Before placement of the framed bent exposed concrete of the assembly bay in the powerhouse of the Luding hydropower plant in Sichuan Province, all necessary technological tests were carried out for raw materials, mix proportion, formwork, jointing, edge and comers, placement, vibration and curing of exposed concrete, and then the optimum combination was found out and used for the construction. Meanwhile, meticulous management was applied to assuring the quality of the exposed concrete during construction quality control, achieving a good outward appearance.
作者 马兰芬
出处 《云南水力发电》 2012年第1期160-165,共6页 Yunnan Water Power
关键词 清水混凝土 工艺试验 质量控制 观感效果 exposed concrete technological test quality control impressions
  • 相关文献

参考文献4

  • 1顾勇新.清水混凝土工程施工技术与工艺[M].北京:中国建筑工业出版社,2006.
  • 2黄辉.清水混凝土在地铁高架桥工程中的应用[J].建筑技术,2006,37(5):350-352. 被引量:8
  • 3中建一局(集团)有限公司.DB11/T464-2007建筑工程清水混凝土施工技术规程[S].2007.
  • 4JGJ169-2009,清水混凝土应用技术规程[S].北京:中国建筑工业出版社,2009.

二级参考文献1

共引文献10

同被引文献4

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部