摘要
针对渠系建筑物涵闸下游水流特点,采用一种适合于低佛氏数消能的新型消能结构-拱网消力池,并对通辽西辽河灌区洪淤渠、孟家段干渠和八一水库泻洪洞采用拱网消能的工程实例进行了分析。结果表明,与普通消力池相比,拱网消力池的池长可缩短50%以上,池深可减少约30%,且消能率可提高20%以上,一般比普通消能措施可节省工程造价30%以上。
The arch net-floor stiling pond are used to many low water head hydraulic structure according to hydraulic property of canal system structure.several engeneerings examples such as hongyu canal of xiliao riv- er, mengjiaduan canal,bayi reservoir are analyzed.the results show that the long of arch net-floor stiling pond is 50 per sent of general stiling basin and the depth and engineering cost can be decrease 30 per cent compared with general stiling basin. The rate of energy dissipation are increased 20 oer cent
出处
《吉林水利》
2012年第3期56-58,共3页
Jilin Water Resources
关键词
拱网
消力池
经济性
投资
工程造价
arch net-floor
stilling pond
conomy
invest
engineering cost