摘要
针对红寺堡110 kV变电站综合自动化系统存在的信息接入量少,反应速度慢,传输信号失真、丢失等问题,基于"35 kV~110 kV无人值班变电站设计规程"对其进行整体改造,改造后的综自系统采用了先进的分散与集中相结合的分层分布式结构,方案实施结果表明:变电站系统容量和信号传输质量明显增强,自动化水平达到了无人值班变电站的技术要求。
Aiming at the problems of the exist information exchange few,response speed slow,transmission signal distortion and lost for the integrated automatization system in Hongsibao 110 kV Substation,based on the 35 kV-110 kV Unattended Substation Design Regulation,makes whole reconstruction for it,after the improvement,the integrated automatization system using advanced delamination and distributed structure with is the distribution in combination with centralization.The schemes implemented results show that the system capacity and signal transmission quality of substation obviously intensify,and automatization level reaches the technology demand of unattended substation.
出处
《宁夏电力》
2012年第1期23-26,共4页
Ningxia Electric Power