论述了在总图设计过程中,土方工程中需要注意的一些重要的因素,包括场地内外的土方平衡、土方松散系数、压实系数及余缺土的处理等。介绍了竖向布置的设计思路,包括竖向布置框架、装置内竖向布置、建筑物的竖向布置、运输系统的竖向布置和场地排雨水等,从整体上对场站竖向布置进行了较为深入的探讨。在经济、安全方面上,土方工程和竖向布置是一对动态平衡,在设计过程中,还要结合总图设计的其他内容,完善土方工程和竖向布置,从而创造出优秀的总图设计。
Some important factors needing to pay attention to the earth work design,including the balance between on and off earth work,loosening coefficient,compaction coefficient,and treatment of the remaining soil or the deficient soil from a certain place to take in were summarized.The design idea of the vertical layout was introduced,including the vertical framework,vertical layout within units,vertical layout of buildings,vertical layout of the transportation system and drainage of rainwater.The earth work and vertical layout were a pair of dynamic balance in the aspects of economy and safety.In the design process,other elements of general layout should be taken into account in order to improve the earth work and vertical layout.Thereby,excellent general layout design could be created finally.
出处
《石油规划设计》
2012年第2期39-41,54,共3页
Petroleum Planning & Engineering