对富春江5#机定子改造时定子铁心装配过程中存在的一些技术难点进行分析,并通过对机组整体结构的研究,提出一些切实可行的技术,保证了定子铁心的安装质量。
This paper analyzes some technical difficulties of the modified stator of No. 5 Fuchunjiang unit in stator core assembly ,process. Some practical on-site technologies are pres- ented by analyzing integral structure of unit. They can ensure assembly quality of stator core.
出处
《防爆电机》
2012年第2期43-45,共3页
Explosion-proof Electric Machine
关键词
定子铁心改造
中心柱调整
大齿压板安装
定子铁心叠装
Modification of stator core
adjustment of center column
installation tooth support
stacking of stator core