摘要
以三峡永久船闸预应力锚索工程施工实践为例 ,详细分析锚索孔倾斜产生的地质条件、工艺因素 ,提出防止产生孔斜的措施 ,并详细介绍钻具保直组合系统。
The prestressed cable technique with high-resolution for the permanent ship gate of the Three Gorges Project is illustrated.The incling factors of hole such as geologic condition,drilling techniques etc.are analyzed,and a new technique is introduced to straight-keeping drill.
出处
《地质灾害与环境保护》
2000年第1期83-84,共2页
Journal of Geological Hazards and Environment Preservation
关键词
预应力对穿锚索
造孔
孔斜
钻孔保直
船闸
prestressed cable
drilling
hole inclination
straight-keeping drill combination