摘要
结合辽宁营口开发区长江路跨铁路立交桥桥墩混凝土施工,探讨了冬季混凝土施工的方法和技术措施,对于搅拌站的保温措施、原材料的加热与保温、混凝土的拌合与运输、混凝土的浇筑与养护以及温度的监测等技术环节进行了详细分析。
Combining with the concrete construction of Changjianglu overpass over railway line in Yingkou Development Zone of Liaoning,the paper discusses the methods and technical measures of winter concrete construction.It also analyzes the heat insulation measures of mixing station,heating and preservation of raw materials,mixing and transformation of concrete,pouring and maintenance of concrete,temperature monitoring and etc.
出处
《河北工程技术高等专科学校学报》
2012年第1期62-65,共4页
Journal of Hebei Engineering and Technical College Quarterly
关键词
混凝土
冬季施工
施工方案
配合比
保温
温度测量
concrete
winter construction
construction scheme
mixture proportion
heat insulation
temperature measurement