摘要
针对新乡市某降压变电站负荷难以满足该地区发展需要的问题,对其进行了改扩建设计:电气主接线采用单母线分段接线,主变压器选择中性点直接接地方式;计算最大/最小运行方式下的短路电流,并据此对部分电气设备进行了选择.
Aiming at the probelm that a Xinxiang City's stepdown transformer substation load doesn't meet the requirement of development in this area,the expansion and improvement design were carried out.The lord wiring used a single bus wiring for subsection,the main transformer chose neutral grounding method directly,the short-circuit current was calcutated at the biggest/minimum operational modes.Therefore,some electrical equiments were selected.
出处
《郑州轻工业学院学报(自然科学版)》
CAS
2012年第2期99-101,共3页
Journal of Zhengzhou University of Light Industry:Natural Science
关键词
变电站扩建
主接线设计
短路电流计算
transformer substation expansion
lord wiring design
short-circuit current calculation