由于送电期限在即,某±500kV换流站继电器室原设计的钢筋混凝土屋面调整为压型钢板混凝土组合屋面,实践证明,调整后的设计方案使施工工期大为节省。文章通过描述该500kV继电器室压型钢板屋面的选型与应用,分析其可行性,供今后类似工程参考。
The concrete roof of relay houses has been changed into profiling steel plate because of deadline in ± 500 kV substation. Its effectiveness is proved feasible and practical and the construction time problems were solved by these measures. Based on the selection of structure and application of the new design, the author analyzes the feasibility and offers a reference for similar projects.
出处
《湖北电力》
2012年第2期15-16,共2页
Hubei Electric Power
关键词
压型钢板
混凝土
组合屋面
继电器室
profiling steel plate
concrete
composite roof
relay houses