摘要
钢管柱逆作法施工时,一方面其水平位移、垂直度等要求非常高,采用普通支撑立柱的施工方法很难达到设计要求;另一方面,在结构设计时,桩身砼与钢管内砼标号不一致,控制好高低标号砼的浇筑质量又是一大难题。通过武汉南国中心一期试桩工程实例,从钢管柱定位、垂直度控制和高低标号砼的浇筑3个方面介绍了逆作法钢管柱施工方法。
Because of high demand on the horizontal displacement and vertical precision in inversion construction of steel pipe column,it is difficult to meet design requirement by general support stud construction method;and the concrete with different marks for pile body and the lining inside of steel pipe in the structure design bring challenge in grouting quality.With an engineering case of Wuhan,the paper introduced inversion construction of steel pipe column in steel pipe column location,verticality control and grouting of different concretes.
出处
《探矿工程(岩土钻掘工程)》
2012年第4期56-59,共4页
Exploration Engineering:Rock & Soil Drilling and Tunneling
关键词
逆作法
钢管柱
调垂架
垂直度控制
砼浇筑
inversion construction method
steel pipe column
verticality adjusting rack
verticality control
concrete grouting