期刊文献+

南水北调中线一期穿黄工程北岸填筑渠道设计 被引量:5

Design of Filling Channel at North Bank Crossing Yellow River of South-to-North Water Diversion Middle Route Phase Ⅰ Project
下载PDF
导出
摘要 南水北调中线穿黄工程北岸填筑渠道位于黄河滩区,填筑高度较高。该段布置有倒虹吸、桥梁等大型交叉建筑物,且基础有地震液化问题,黄河洪水上滩防护问题,防渗要求高。侧重阐述了渠道填筑设计、防渗设计、防护设计、防冻胀设计及基础处理等主要技术问题,这些技术问题在南水北调中线工程中具有一定代表性,妥善解决好这些问题,具有较显著的工程应用价值。 The embankment channel in the north bank of the middle route crossing the Yellow River of the South-to-North Water Diversion Project is located in the floodplain with a high filling height.The invert siphons,bridges,and other large-scale crossing structures exist in the area.Moreover,the foundation of this area has problems with seismic liquefaction and flood protection,thus it requires a high standard for seepage control.This paper discussed the main technical problems including the design of channel filling,design of seepage control,protection design,design of frozen prevention,and foundation treatment.These technical problems are representative occurring in the South-to-North Water Diversion Middle Route Project,and thus the solutions to solve these problems have remarkable engineering application values.
出处 《南水北调与水利科技》 CAS CSCD 北大核心 2012年第2期26-29,共4页 South-to-North Water Transfers and Water Science & Technology
关键词 填筑土料 渠道防渗 基础处理 排水设计 南水北调 filling soil material channel seepage control foundation treatment drainage design South-to-North Water Diversion
  • 相关文献

参考文献7

  • 1黄河勘测规划设计有限公司.南水北调中线一期穿黄工程初步设计报告[R].2004.
  • 2黄河勘测规划设计有限公司.南水北调中线一期穿黄工程招标设计报告[R].2005.
  • 3SL 18-2004 渠道防渗工程技术规范[S].
  • 4黄河勘测规划设计有限公司.南水北调中线一期穿黄工程渠道衬砌及防渗结构优化设计报告[R].2008.
  • 5SL 23-2006 渠系工程抗冻胀设计规范[S].
  • 6龚晓南.地基处理手册(第三版)[K].中国建筑工业出版社,2008:165-215.
  • 7罗字生.湿陷性黄土地基处理[M].中国建筑工业出版社,2008:6080.

共引文献62