期刊文献+

东山供水工程9号隧洞施工方案比选 被引量:1

Comparing and Selecting Plan to Construct NO.9 Tunnel in Dongshan Water Supply Project
下载PDF
导出
摘要 东山供水工程的9号隧洞全长22.64km,其中土洞长2.3km,岩石洞长20.34km,隧洞地形条件复杂,施工支洞布置难度较大,通过比较分析,确定合理的施工方法,即土洞段采用钻爆法施工,岩石洞段采用隧洞掘进机施工。 In Dongshan Water Supply Project,the total length of NO.9 tunnel is 22.64 km,in which,the length of soil tunnel is 2.3 km,and the length of rock tunnel is 20.34 km.The tunnel's topographical condition is complex,to set up construction drifts is difficult.By means of comparing and selecting alternative plans,the reasonable construction methods are determined: drill-blast tunneling method is adopted in soil tunnel section,TBM tunneling method in rock tunnel section.
作者 闫海雷
出处 《山西水利科技》 2012年第2期31-33,41,共4页 Shanxi Hydrotechnics
关键词 9号隧洞 钻爆法施工 隧洞掘进机(TBM)施工 比选 NO.9 tunnel drill-blast tunneling method TBM tunneling method comparison and selection
  • 相关文献

同被引文献3

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部