摘要
在深入探讨工程项目实施过程中进度计划与资源计划协调运行的同时 ,提出了在资源限制性条件下对工期进行优化的“RSM”法 ,并对该方法繁复的计算过程进行了改进 ,从而可以大大减少手算工作量、节省计算机内存。
This paper investigates the coordinated operation of the progress planning with the resource planning when carrying out engineering projects and puts forward a method of 'RSM' under the resource limit conditions. Then, the 'RSM' was improved to avoid complicated calculation. This method not only reduces the calculating work by hand but saves computer's memory as well, making the time-resource optimization work more quick and convenient.