500kV输电线路半掏挖斜插角钢基础施工

Construction of half-dig cross-pillar base angel steel lean-inserting foundation on 500 kV transmission line
下载PDF
导出
摘要 半掏挖斜插基础具有如下特点:基础底部为掏挖部分,砼浇制时可以土代模;立柱和插入角钢的坡度与铁塔腿部主材坡度一致;基础立柱较高而主角钢悬于半空中未达到基础底部,基础顶面为菱形。施工中采用半掏挖斜柱加高全方位高低腿形式的基础,不仅施工工器具简单,操作方便,通用性强,施工优良品率高,经济效益也很明显,其经济性在山区施工中尤其突出。插入角钢的安装与定位都简单易行,与传统的模拟塔腿定位的方法相比劳动强度大大降低,工作效率显著提高。 Half-dig cross-pillar base angel steel lean-inserting foundation has features as follows: the foundation is digging part;the slope of pillar and steel lean-inserting is consistent with that of tower leg;foundation top is diamond.Half-dig cross-pillar base and tower with legs at different height is applied in construction because instruments are simple,effective and economic.Compared with traditional tower leg location,the method is efficiency.
作者 周清泉
出处 《江西电力》 2012年第1期41-43,56,共4页 Jiangxi Electric Power
关键词 500KV线路 半掏挖 斜插入角钢 高立柱基础立模 500 kV transmission line half dig angel steel lean-inserting column foundation framework
  • 相关文献

参考文献1

  • 1GB50233-2005.110-500kV架空送电线路施工及验收规范[S].

共引文献34

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...