摘要
为了消除舾装对坞期的影响,通过调整船体焊接过程中的变形量,把轴系相关工程提前至传统条件之前,从而达到缩短坞期的目的,在确定的坞期内寻求船体和舾装的最佳平衡。
In order to avoid the effects of dock term from outfitting works,the shaft works should be done before traditional modus by controlling the welding distortion in a certain range to shorten the dock term.The balance of hull works and outfitting works in fixed dock term of shipbuilding was investigated.
出处
《船海工程》
2012年第3期20-21,共2页
Ship & Ocean Engineering
关键词
轴系工程
主机搭载
预变形量
镗孔
偏心衬套
shaft works
main engine installation
distortion in advance
boring
bush with eccentricity